NextDecade Provides Q1 And Early Q2 2025 Business Update
Author: Benzinga Newsdesk | May 06, 2025 05:03pm
Significant Recent Developments
Construction
- Under the EPC contracts with Bechtel Energy Inc. (Bechtel), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of March 2025:
- The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 42.8%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 87.9% complete, procurement was 76.3% complete, and construction was 14.1% complete.
- The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 17.8%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 41.9% complete, procurement was 37.2% complete, and construction was 0.8% complete.
- In February 2025, the Company provided additional information regarding its development of additional liquefaction capacity at the Rio Grande LNG Facility beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 million tonnes per annum (MTPA) once constructed and placed into operation.
- Train 6, with expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. A pre-filing application with FERC for Train 6 is expected in 2025, and a full FERC application is expected in early 2026.
- Trains 7 and 8, with a total expected LNG production capacity of approximately 12 MTPA, are being developed on the site outside of the existing levee.
Strategic and Commercial
- In January 2025, the Company requested a pricing refresh under the August 2024 EPC contract with Bechtel for Train 4 and related infrastructure. The pricing refresh is in process and is expected to be completed in the second quarter of 2025.
- In April 2025, the Company announced a 20-year LNG SPA with a subsidiary of Saudi Aramco (Aramco), pursuant to which the Aramco subsidiary will purchase 1.2 MTPA of LNG From Train 4 at the Rio Grande LNG Facility for 20 years, on a free on board (FOB) basis at a price indexed to Henry Hub, subject to a positive FID on Train 4.
- In April 2025, the Company announced that TotalEnergies exercised its LNG purchase option with respect to Train 4 and the Company entered into a 20-year LNG SPA with TotalEnergies, pursuant to which TotalEnergies will purchase 1.5 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub, subject to a positive FID on Train 4. The Company believes sufficient long-term commercial agreements are now in place to support a positive FID on Train 4.
Financial
- In April 2025, Rio Grande LNG, LLC elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million and is expected to reduce related commitment fees by approximately $2 million annually.
Regulatory
- In March 2025, the U.S. Court of Appeals for the D.C. Circuit issued a revision to its August 2024 decision regarding the Company's FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC is to consider the issue of an SEIS in view of several executive orders issued since January 20, 2025.
- In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. A final SEIS is expected in July 2025.
Posted In: NEXT